Sam’s East Inc.

Project Location:

300 Berlin - Cross Keys Rd, Williamstown, NJ

Description of Work:

Installation of sheet pile shoring system. Excavation for new underground storage tanks and piping systems. Installation of 3-20,000 gallon Xerxes Fiberglass Double Wall Underground Storage Tanks. Installation of new tank sumps, spill & overfill protection devices. Installation of new Veeder Root TLS450 Tank Monitor and Leak Detection System. Installation of 7 new fuel islands. Installation of new OPW double wall flexible piping system. Installation of new concrete canopy and kiosk foundations. Installation of new concrete tank and drive mats. Installation of new Kiosk Building. Installation of new concrete filled pipe bollards and signage.

Work Performed for: G. M. Crisalli & Associates, Inc.
Status: Completed November 2018

Click on the images below to enlarge.