SPD Washer/Disinfector Upgrade Project

Project Location:

345 E 24th Street, New York, NY 10010

Description of Work:

Demo and remove 5 existing washer /disinfectors. Perform all required ICRA, site prep, mechanical, plumbing and electrical upgrades. Modified steam supply and return piping/valves. Modified hot and cold-water piping/valves/gauges. Modified D/I water lines/valves and gauges. Perform all demolition and drywall modifications. Prepped, leveled and refinished epoxy floors to prep for installation of 5 new Belimed WD290 Washer/Disinfectors, New Conveyors & Automation with Automatic Return Gate.

Work Performed for: NYU Dental School
Status: Project Completed January 2, 2020